Orlando International Airport (MCO) has launched upgraded automated people mover (APM) services to Gates 100–129. This marks the first major operational milestone in a 253 million USD project to replace and modernise its Gate Link system.
The upgraded service entered operation on 13 October, introducing new vehicles and modernised infrastructure on the first of two tracks serving the gates.

The Gate Link Replacement Project forms part of the airport’s wider 6.9 billion USD Capital Improvement Programme, which aims to modernise facilities and improve passenger journeys.
The work includes replacing running surfaces, power distribution equipment, vehicle controls, communications and operating systems. Platform screen doors are also being installed as part of the upgrades. Each new set of Gate Link cars can carry up to 240 passengers.
With the first track now operational, work will move to the second track serving Gates 100–129. Once this section is complete, the project will progress to Gates 70–99, where both tracks, the trams and associated systems will be replaced or upgraded.
The phased approach allows the newly upgraded track to carry passengers while work continues on the remaining infrastructure.
Lance Lyttle, CEO of the Greater Orlando Aviation Authority, said:Every journey through MCO is part of a larger story. Through our $6.9 billion Capital Improvement Program, we are building an airport for the future, and this Gate Link milestone brings that vision to life with a smoother, more dependable experience for passengers.
Orlando International Airport serves nearly 58 million passengers annually across Terminals A, B and C. The airport is also connected to an intermodal terminal facility offering high-speed passenger rail services.
The Gate Link replacement is intended to improve the reliability of the automated transport system connecting passengers with their gates as the wider airport continues to modernise.